01Core process

The temporary works procedure

Follow the controlled process from identification and design brief through checking, implementation, use and dismantling.

02People

Roles, appointments & authority

Know the DI, TWC, TWS, designer, checker and contractor interfaces—and who is authorised to stop unsafe work.

03Leadership

The 4Cs

Apply communication, co-operation, co-ordination and competence to realistic site decisions.

04Records

Design briefs & registers

Recognise the information needed for an adequate brief and the register entries that maintain control.

05Assurance

Design checks & categories

Understand how complexity, novelty and consequence inform an appropriate independent checking approach.

06Site control

Inspection, permits & change

Use hold points, permits and escalation to prevent loading, alteration or dismantling without authority.

Practice workspace · TWC

Make the decision. Then learn the reason.

These are original, course-aligned revision questions. Select the strongest answer before reading the explanation.

Question 1 of 8TWC + TWS
4Cs

Which group correctly states the 4Cs emphasised in temporary works management?

Choose one answer. The explanation will appear immediately.

Site judgement drills

What would you do next?

Use the reveal panels to rehearse a short, decisive response suitable for a course discussion or site briefing.

01Excavation support arrives without identifiable design information+
Strong response

Quarantine the equipment or affected work, confirm the intended system and configuration, and refer the missing design information through the TWC. Do not permit installation from memory or a supplier brochure.

02A crane outrigger position moves 1.5 m to avoid a service+
Strong response

Treat the move as a change. Stop set-up at that position and have the ground, support arrangement, geometry and resulting loads assessed through the controlled design and checking process.

03A completed prop installation is struck by mobile plant+
Strong response

Stop work, establish an exclusion zone, prevent loading or removal, notify the TWC and arrange a competent assessment. Damage or movement cannot be accepted from appearance alone.

Advanced design challenge · 25 questions

Try If You Dare!

This is the hard set: load paths, stability, ground, falsework, working platforms, propping and design change under pressure. Every question is original and includes a technical explanation.

Designer-level judgementThink beyond the arithmetic. Identify the governing failure mode, assumption or temporary state.
Temporary works designDIFFICULT
Bearing pressure

A crane outrigger applies 420 kN vertically. The stated allowable ground bearing pressure is 150 kPa. Ignoring mat self-weight for this first sizing step, what is the minimum bearing area before eccentricity, settlement, mat strength and ground variability are checked?

Choose the strongest design response. The technical explanation appears after your answer.

Independent advanced revision only. These are not CITB examination questions and do not replace project-specific design, checking, current standards or your organisation's temporary works procedure.

Microsoft Forms-style example

A ready-made Q&A structure for delegates.

This working example shows how a self-marking revision form can be structured. It is a demonstration, not an embedded Microsoft form.

TW
Temporary Works Revision CheckKnowledge check · 3 questions
Independent revision exercise

Answer every question, then submit to reveal your score and marking guide.

* Required
1. Who should authorise a departure from the issued temporary works design? *
2. Which action best protects a temporary works hold point? *
3. Training alone proves that a person is competent for a TWC or TWS appointment. *